Hospital AHU Replacement with Dual EC Blowers

Hospital AHU Replacement with Dual EC Blowers

Existing hospital air handling unit before 5,000 CFM AHU replacement
GRR Cooling Experts technicians removing the existing hospital AHU during replacement
New hospital AHU filter section with two-stage filtration during installation
Completed 5,000 CFM hospital AHU replacement with dual direct-drive EC blowers
Existing hospital air handling unit before 5,000 CFM AHU replacement
GRR Cooling Experts technicians removing the existing hospital AHU during replacement
New hospital AHU filter section with two-stage filtration during installation
Completed 5,000 CFM hospital AHU replacement with dual direct-drive EC blowers

Overview

GRR Cooling Experts completed a full hospital air handling unit replacement in Connecticut, replacing the existing AHU with a new double-wall system designed for 5,000 CFM at 5.0 in. ESP.

The new AHU integrates two-stage filtration, steam preheat and chilled-water coil sections, two direct-drive EC blowers, new piping connections, and custom intake and discharge duct transitions into the existing hospital infrastructure.

The work was coordinated around a limited Friday-Saturday shutdown window, requiring demolition, equipment installation, piping, duct adaptation, electrical work, and system integration to follow a controlled field sequence.

See the field execution behind this 5,000 CFM hospital AHU replacement, from existing conditions and installation work to the completed double-wall system.

More GRR field projects on video:

The Challenge

A complete AHU replacement inside an existing hospital requires more than selecting new equipment.

The original AHU and its fresh-air plenum, filter section, preheat coil, chilled-water coil, and blower section had to be disconnected, demolished, and removed while the surrounding ductwork, piping, electrical infrastructure, and existing controls remained part of the building system.

The project also had to be organized around a two-day Friday-Saturday shutdown window, making equipment fit-up, trade coordination, duct transitions, piping modifications, and electrical readiness part of the installation plan before the shutdown began.

The Solution

GRR installed a new double-wall AHU and adapted the complete replacement package to the existing hospital infrastructure.

The project scope included:

๐Ÿ”น New fresh-air and return plenum with two dampers and an access door
๐Ÿ”น Two-stage filtration using V-bank and 2" pleated filters
๐Ÿ”น New steam preheat coil
๐Ÿ”น New 6-row chilled-water coil with stainless-steel gravity drain pan
๐Ÿ”น Two direct-drive EC blowers with gravity backdraft dampers
๐Ÿ”น New dedicated control panel and wiring to the EC blowers
๐Ÿ”น Modification and reconnection of chilled-water and steam piping
๐Ÿ”น New intake and discharge duct transitions connected to the existing duct system
๐Ÿ”น Insulation and sealing of new piping and ductwork

System Specifications

๐Ÿ”น Airflow: 5,000 CFM
๐Ÿ”น External Static Pressure: 5.0 in. ESP
๐Ÿ”น AHU Construction: Double-wall, painted
๐Ÿ”น Fan Configuration: Two direct-drive EC blowers
๐Ÿ”น Filtration: V-bank + 2" pleated filters
๐Ÿ”น Cooling: 6-row chilled-water coil
๐Ÿ”น Heating: Steam preheat coil
๐Ÿ”น Shutdown Window: Friday-Saturday

Project Boundaries

Existing controls and control valves remained by others. Main electrical power to the new control panel and final testing, adjusting, and balancing (TAB) were also provided by others.

Outcome

The completed project replaced the existing hospital AHU with a new 5,000 CFM double-wall air handling system integrated into the facilityโ€™s existing ductwork, piping, electrical, and controls infrastructure.

The final configuration combines new filtration, heating and cooling coil sections, dual direct-drive EC blowers, custom duct transitions, and modified piping within one coordinated AHU replacement scope.

The project demonstrates how complete air handling equipment replacement can be engineered around existing hospital conditions and a limited shutdown window rather than treated as a simple equipment swap.

GRR Cooling Experts. Precision HVAC Retrofit Engineering for Critical Environments.

Request an HVAC Retrofit Review

If your hospital, healthcare facility, or commercial building is evaluating an aging AHU, full air handling unit replacement, or HVAC retrofit under a limited shutdown window, GRR Cooling Experts can review the existing conditions and help define a practical replacement approach.


Overview

GRR Cooling Experts completed a full hospital air handling unit replacement in Connecticut, replacing the existing AHU with a new double-wall system designed for 5,000 CFM at 5.0 in. ESP.

The new AHU integrates two-stage filtration, steam preheat and chilled-water coil sections, two direct-drive EC blowers, new piping connections, and custom intake and discharge duct transitions into the existing hospital infrastructure.

The work was coordinated around a limited Friday-Saturday shutdown window, requiring demolition, equipment installation, piping, duct adaptation, electrical work, and system integration to follow a controlled field sequence.

See the field execution behind this 5,000 CFM hospital AHU replacement, from existing conditions and installation work to the completed double-wall system.

More GRR field projects on video:

The Challenge

A complete AHU replacement inside an existing hospital requires more than selecting new equipment.

The original AHU and its fresh-air plenum, filter section, preheat coil, chilled-water coil, and blower section had to be disconnected, demolished, and removed while the surrounding ductwork, piping, electrical infrastructure, and existing controls remained part of the building system.

The project also had to be organized around a two-day Friday-Saturday shutdown window, making equipment fit-up, trade coordination, duct transitions, piping modifications, and electrical readiness part of the installation plan before the shutdown began.

The Solution

GRR installed a new double-wall AHU and adapted the complete replacement package to the existing hospital infrastructure.

The project scope included:

๐Ÿ”น New fresh-air and return plenum with two dampers and an access door
๐Ÿ”น Two-stage filtration using V-bank and 2" pleated filters
๐Ÿ”น New steam preheat coil
๐Ÿ”น New 6-row chilled-water coil with stainless-steel gravity drain pan
๐Ÿ”น Two direct-drive EC blowers with gravity backdraft dampers
๐Ÿ”น New dedicated control panel and wiring to the EC blowers
๐Ÿ”น Modification and reconnection of chilled-water and steam piping
๐Ÿ”น New intake and discharge duct transitions connected to the existing duct system
๐Ÿ”น Insulation and sealing of new piping and ductwork

System Specifications

๐Ÿ”น Airflow: 5,000 CFM
๐Ÿ”น External Static Pressure: 5.0 in. ESP
๐Ÿ”น AHU Construction: Double-wall, painted
๐Ÿ”น Fan Configuration: Two direct-drive EC blowers
๐Ÿ”น Filtration: V-bank + 2" pleated filters
๐Ÿ”น Cooling: 6-row chilled-water coil
๐Ÿ”น Heating: Steam preheat coil
๐Ÿ”น Shutdown Window: Friday-Saturday

Project Boundaries

Existing controls and control valves remained by others. Main electrical power to the new control panel and final testing, adjusting, and balancing (TAB) were also provided by others.

Outcome

The completed project replaced the existing hospital AHU with a new 5,000 CFM double-wall air handling system integrated into the facilityโ€™s existing ductwork, piping, electrical, and controls infrastructure.

The final configuration combines new filtration, heating and cooling coil sections, dual direct-drive EC blowers, custom duct transitions, and modified piping within one coordinated AHU replacement scope.

The project demonstrates how complete air handling equipment replacement can be engineered around existing hospital conditions and a limited shutdown window rather than treated as a simple equipment swap.

GRR Cooling Experts. Precision HVAC Retrofit Engineering for Critical Environments.

Request an HVAC Retrofit Review

If your hospital, healthcare facility, or commercial building is evaluating an aging AHU, full air handling unit replacement, or HVAC retrofit under a limited shutdown window, GRR Cooling Experts can review the existing conditions and help define a practical replacement approach.